  • Concreting Between 2K Yard Project

Concreting Between 2K Yard

Client

Keppel Shipyard Batangas

Location

Keppel Shipyard, Bauan, Batangas

Project Type

Industrial

Project Status

Completed

Details

The project took place in between July 15 to August 3, 2013. Primarily supplied manpower, labor, materials, equipments, consumable tools and direct supervision to do additional concrete pavement in between K2 sub-station and north of block assy.